The following updates have been added to RamBase Cloud ERP:
Production
Extended options in Rework
Classification: USEFUL
Having options for handling the various causes for production delay is critical in lean manufacturing.
We are therefore extending our current rework functionality by adding the option to rework Product unit(s) (LCM) while Production work order (PWO) is in Status 4 - Pending scheduled production start or Status 5 - In production.
The functionality is also planned to be available for Production work orders (PWO) in Status 2 - Pending purchase or production and Status 3 - Pending goods reception, in the near future.
This extension comes with fewer clicks for the user tasked with handling the delay, as the procedure only requires handling in the Production work order (PWO) and the Production work order assignments (PWOSARLINKS) applications, and then following up the new Production work order (PWO) from the Production work orders (PWOMENU) application.
Listed below are the current approaches to handling rework in RamBase:
Perform Rework with quantity more than 1, no parts to be changed
Perform Rework on single quantity where parts needs to be replaced
Rework Product unit(s) (LCM) while Production work order (PWO) is in Status 2, 3, 4 or 5
To access step-by-step procedures for the different approaches, click here.
Admin
Minor fixes in the Duties (DUTY) application
Classification: USEFUL
The following improvements have been added to the Privileges tab in the Duties (DUTY) application:
In the Restrictions column, replaced Filter builder with the improved Add/edit filter and Add/Edit fields buttons.
Note that when adding filters, the privilege filters needs to be in API format (OData). Client filters can be entered and converted to valid API format.
General improvements to the user experience when editing a privilege.
Knut Sætre Waka
The following updates have been added to RamBase Cloud ERP:
Production
Extended options in Rework
Classification: USEFUL
Having options for handling the various causes for production delay is critical in lean manufacturing.
We are therefore extending our current rework functionality by adding the option to rework Product unit(s) (LCM) while Production work order (PWO) is in Status 4 - Pending scheduled production start or Status 5 - In production.
The functionality is also planned to be available for Production work orders (PWO) in Status 2 - Pending purchase or production and Status 3 - Pending goods reception, in the near future.
This extension comes with fewer clicks for the user tasked with handling the delay, as the procedure only requires handling in the Production work order (PWO) and the Production work order assignments (PWOSARLINKS) applications, and then following up the new Production work order (PWO) from the Production work orders (PWOMENU) application.
Listed below are the current approaches to handling rework in RamBase:
Perform Rework with quantity more than 1, no parts to be changed
Perform Rework on single quantity where parts needs to be replaced
Rework Product unit(s) (LCM) while Production work order (PWO) is in Status 2, 3, 4 or 5
To access step-by-step procedures for the different approaches, click here.
Admin
Minor fixes in the Duties (DUTY) application
Classification: USEFUL
The following improvements have been added to the Privileges tab in the Duties (DUTY) application:
In the Restrictions column, replaced Filter builder with the improved Add/edit filter and Add/Edit fields buttons.
Note that when adding filters, the privilege filters needs to be in API format (OData). Client filters can be entered and converted to valid API format.
General improvements to the user experience when editing a privilege.