Production: Change in Production work orders (PWO) material date information

Classification:  USEFUL


The Production work order (PWO) shows some information about the available date for the material and if the necessary material/parts have received a new delay for one or more of the materials/parts.


This will now be upgraded, the fields used for this will be moved to another table on the PWO.
This upgrade will also provide a better and more informative overview of the material status.


The information has the same placement as before, but now with some more details.
The text after the Confirmed MaterialDate on the PWO can now be:

  • Unconfirmed - One or more of the material/part/sub production/external operation has not been ordered or has not been confirmed.

  • A date - All required, but not yet received material/part/sub production/external operation is confirmed. The last confirmed date is shown.

  • Stock - All material/part/sub production is in stock.

  • HiLoStock - Production end date is too early/too late (in days) for the needed delivery. Negative value = too late.

  • MaterialDelayedDays – Last confirmed material/part/ sub production/external operations is xx days too early/too late for the required date. Negative value = too late.

Release date: February 23rd 2021 (Late afternoon because of the process to move contents to new fields)