FAQ: Production

'Change price' on a production Goods reception (SSA) - will this update prices on the production work order (PWO)?
'Change price' on a goods reception (SSA) for a part does not trigger a recalculation of the price on the associated production goods reception...
Fri, 30 Jul, 2021 at 2:10 PM
What is the correct process when scrapping quantity on a production work order (PWO) and changing the total quantity on orders?
1. If the customer is aware of the change (that X number of products have been scrapped):     Forward the produced quantity on the sales ...
Thu, 29 Jul, 2021 at 10:23 AM
What can affect the subtotals on a KIT and the price on a finished production and how does the calculations work?
Here is an explanation as to how the calculations work and what can affect the subtotals on a KIT and the price on a finished production, a so-called '...
Thu, 27 May, 2021 at 9:37 AM
How can a user be added to the list of people who are able to approve measurement documents (MSR)
The user can be added to the group defined for this using the 'add person to group' icon. The specific group is found with the following restricti...
Wed, 12 May, 2021 at 1:51 PM
Is Department (DEP) and project (PRJ) on a customer order (COA) copied to the production work order (PWO)?
Department (DEP) and project (PRJ) is copied from the customer order (COA) to the production work order (PWO) when the production is created based on a spec...
Wed, 12 May, 2021 at 12:30 PM
How can a user be added to the list of people who are able to approve a products structure?
If you have the access to approve product structures, you are be able to give another person access to approve. Enter on ‘Production’ that is highlighted be...
Mon, 3 May, 2021 at 3:06 PM
Why is the produced product linked to a customer order and how can I release it for another customer??
When a production order is created from PRODPLAN ‘Pending by Order’ folder, the production work order (PWO) will be linked to the specific customer/customer...
Wed, 19 May, 2021 at 10:49 PM
How can I choose between several measurement (MSR) templates on a specific production order (PWO)?
Define a template with the specific measurements that are to be included in documents of  Type = KCI (Key Characteristics Inspection).  When you create a ...
Wed, 5 May, 2021 at 4:09 PM
How can one undo a part replacement on an LCM (Life Cycle Management document)?​​
There is no option to reverse a part change on a Life Cycle Management document (LCM). One will have to change back to the required part and in addition, cr...
Fri, 5 Feb, 2021 at 7:25 AM
How does the ‘Delink a production order’ function work?​​
The Delink function is designed for manual handling of first to delink and then to relink material in a production order (PWO). ‘Delink production order’ p...
Fri, 5 Feb, 2021 at 7:24 AM